Environmental Quality Management, Inc.EQ logo

Remediation and Re-Utilization Services

EQ's remediation and re-utilization group have successfully completed over 500 site assessments and remediation projects nationwide involving soil and groundwater contamination from active as well as former industrial sites.

Contact EQ for more information

Conjecture Mine Remediation Project

MIne The removal action for the Conjecture Mine is being performed to mitigate the release of hazardous substances, including arsenic, lead, and manganese, from waste rock dumps and sediment along Gold Creek. The removal action is involving the removal of contaminated mine waste materials from the site for deposition in a nearby waste repository and the construction of a clean stream corridor for Gold Creek.
 
The removal action at Conjecture Mine is part of a comprehensive approach by EPA and the United States Forest Service to address mine waste contaminants in the Gold Creek watershed. The Conjecture Mine site, which is situated near the headwaters of Gold Creek, extends more than one-third mile along Gold Creek. The upper portion of the site contains four large waste rock dumps, scattered deposits of disturbed and eroded materials, and stream sediments. The North Dump is the largest waste dump at the site and is bisected by Gold Creek. A waste rock dump on the southwest side of the site, referred to herein as Southwest Waste Rock Dump, forms the western bank of Gold Creek, and a third waste rock dump, Mid-South Waste Rock Dump is located on the south side of the site between Gold Creek and a Gold Creek tributary. The fourth dump, the Southeast Waste Rock Dump, is located below two collapsed adits east of the Gold Creek tributary.

FINISHED CREEKApproximately 40,000 loose yd3 of waste materials is being removed in these locations for deposit in the nearby USFS repository.  Identification of mine-waste materials for removal will be accomplished by field screening, including visual observation and analysis by field portable x-ray fluorescence (FPXRF). An estimated amount of 2 feet of over-excavation is expected and is included in the volume estimates. Following removal of the contaminated materials, the excavated areas is being backfilled as necessary using fill from borrow sites on USFS land in the vicinity of the site approximately 40,000 yd3 of topsoil. The ultimate goal is to create a clean stream corridor along Gold Creek and its tributaries in these areas.

A clean stream corridor has been constructed for Gold Creek and its tributaries restoring the hydraulic capacity and preventing erosion and liberation of metals contamination. Construction of this corridor included removal of approximately 7,500 yd3 of contaminated sediment and reshaping the topography to allow the water to flow through a clean and stable corridor. Regrading efforts are substantial, and include moving roughly 100,000 yd3 of material, to prevent waste rock from coming into contact with surface water.

The entire crew is staying onsite in a 25 room mobile camp with two cooks that take care of all meals. The entire site is completely self-contained with lodging, food, satellite internet, satellite phones and cell phone boosters.
 camp

 

 

 

 

 

 

 

Contact EQ...

remediationA complete listing of EQ's Remediation and Re-utilization Services is available in brochure format.

EQ's multidisciplinary staff provide key services covering the total spectrum of your environmental engineering requirements from project planning to complex site assessment/remediation projects. This listing contains just a few of the projects that EQ has completed for our clients.

If you would like additional information or if you have any questions concerning these projects please contact Bob McCullough at (800) 229-7495.

Top • Back

 

 

 

environmental
news & more

RSS feed for EQM
What is RSS?
EPA Proposes Interstate Transport Rule to Reduce Ozone and Fine Particle Pollution
On July 6, 2010, the U.S. EPA announced the proposal of regulations to reduce power plant emissions of sulfur dioxide (SO2) and nitrogen oxides (NOx) that cross State lines.
National Emission Standards for Hazardous Air Pollutants for Reciprocating Internal Combustion Engines
On March 3, 2010, the U.S.EPA promulgated changes to the NESHAP for Reciprocating Internal Combustion Engines (RICE), 40 CFR Part 63 Subpart ZZZZ, which expanded upon the existing RICE standards.
Significant New Use Rules Issued For 17 Chemicals; Two Pose Risks, EPA Says
On June 28, 2010, the U.S. EPA announced that it is issuing direct final significant new use rules (SNURs) for 17 chemicals, subjecting any proposed manufacture or importation of the substances designated as "new" to 90-day review by the agency.
U.S. EPA Requires Four Industrial Sectors to Report Greenhouse Gas Emissions
On June 29, 2010, the U.S. EPA announced a final rule that requires facilities in four industrial sectors to report greenhouse gas emissions.
Tire Companies Oppose EPA Proposal to Consider Whole Scrap Tires Solid Waste
Tire manufacturers and other groups say they are concerned that the U.S. EPA will be eliminating an important market for used tires if it decides that whole scrap tires are solid waste when incinerated rather than burned as fuel.